Only five days after delivery, new Sarajevo tram already damaged

NEWS 01.04.202421:30 0 komentara
N1

Sarajevo Canton’s Transportation Minister Adnan Steta expressed his disappointment on Facebook, on Monday, after the new trams for which the BiH capital waited for 40 years have already been damaged.

“Edo engraved his name in the new tram and caused enormous damage to all citizens. It took five days for the first such case to happen. [This is] sad and embarrassing. Video footage from the vehicle and moments of property destruction will be handed over to the institutions for further action and sanctioning,” said Steta.

The new Sarajevo trams are equipped with modern equipment, they are low-floor vehicles with a capacity of 180 passengers, with 79 seats. They have air conditioning, a passenger counting system, wi-fi, USB ports for mobile phones and are fully adapted for people with disabilities.

Video surveillance inside and outside the vehicle enables greater passenger safety and security control in vehicles.

The chairs were chosen by the citizens of Sarajevo Canton at the Open Day of the Ministry of Transport of the KS.

The delivery of trams is taking place in accordance with the planned dynamics.

The plan is to have two more trams in traffic in April, four more in May, and the remaining six in June, July and August. In this way, by the beginning of the next school year, all 15 trams will be in traffic.

There will be no advertisements on the new Sarajevo trams. The trams have undergone testing and testing, which will be adapted to all trams during the delivery and handover of the trams so that they can be in traffic immediately after the handover. Tram drivers underwent training with representatives of the Stadler company in Poland and Sarajevo.